The following is the 2-week look ahead update:
Construction
Anticipated construction activities over the next 2 weeks starting April 12th week
- Stage 4 traffic remains in place along Terry Fox Drive. Line painting refreshed this past week.
- Continue the storm sewer works along Didsbury Road (east) and commence Earl Grey Drive Extension.
- Continue Terry Fox OP abutment forming.
- Commence Terry Fox south side stage 1 foundations.
Traffic
The following are the current and upcoming traffic impacts for your community.
Lane Closures
Anticipated lane closures over the next 2 weeks, continuing the week of April 12th:
- Stage 4 traffic configuration along Terry Fox Drive – two North-bound lanes open, two South-bound lanes open traffic between approximately Campeau Drive to Hwy 417 WBL exits i.e., no lane closures
- Encroachment/flagging as necessary, along Didsbury Road East near Earl Grey Drive.
Pedestrian Detours
- No impacts anticipated, north-bound cyclists and pedestrians along Terry Fox Drive are detoured to the temporary multi-use pathway along the East side of Terry Fox Drive.
OC Transpo Detours
- No route impacts anticipated. Temporary Bus Stops applied by OC Transpo along Terry Fox where necessary.
Other
- Access to residents and business are being maintained
- Ongoing discussions with the BIA
- Schedule and Traffic impacts are subject to change and are subject to conditions such as weather, material/labour supply and availability, unforeseen items and conditions