The following is the 2-week look ahead update for the Earl Grey Underpass project: Construction Anticipated construction activities over the next 2 weeks starting April 26th week Stage 4 traffic remains in place along Terry Fox Drive. Continue the storm sewer works along Didsbury Road (east) and Earl Grey Drive…