Sharing the latest 2-week look ahead update for the Earl Grey Drive Extension project.
Construction
Anticipated construction activities over the next 2 weeks starting November 9th week
- Stage 4 traffic remains in place along Terry Fox Drive. Transfer for Stage 6.
- Didsbury Road (east) open.
- Retaining walls along Earl Grey Drive extension.
- Continue Terry Fox Stage 1 overpass works; paving.
- Commence Terry Fox Stage 2 overpass works; excavations.
Traffic
The following are the current and upcoming traffic impacts for your community.
Lane Closures
No anticipated lane closures over the next 2 weeks, continuing the week of November 9h
- Stage 4 traffic configuration along Terry Fox Drive – two North-bound lanes open, two South-bound lanes open traffic between approximately Campeau Drive to Hwy 417 WBL exits.
- Didsbury Road East at Terry Fox Drive is open.
- Targeting Stage 6 traffic configuration along Terry Fox Drive – two North-bound lanes open, two South-bound lanes open traffic between approximately Campeau Drive to Hwy 417 WBL exits in early to Mid-November. Short term lane closures during transfer to new traffic stage.
Pedestrian Detours
- No impacts anticipated, north-bound cyclists and pedestrians along Terry Fox Drive are detoured to the temporary multi-use pathway along the East side of Terry Fox Drive. New pathway configuration for Stage 2/3 bridge works in progress.
OC Transpo Detours
- No route impacts anticipated. Temporary Bus Stops applied by OC Transpo along Terry Fox where necessary.
Other
- Access to businesses maintained throughout.
- Ongoing discussions with the BIA
- Schedule and Traffic impacts are subject to change and are subject to conditions such as weather, material/labour supply and availability, unforeseen items and conditions.