The following is the 2-week look ahead update for the Earl Grey Underpass project:

Construction

Anticipated construction activities over the next 2 weeks starting April 26th week

  • Stage 4 traffic remains in place along Terry Fox Drive.
  • Continue the storm sewer works along Didsbury Road (east) and Earl Grey Drive Extension.
  • Continue Terry Fox south side stage 1 foundations.

Traffic

The following are the current and upcoming traffic impacts for your community.

Lane Closures

Anticipated lane closures over the next 2 weeks, continuing the week of April 26th:

  • Stage 4 traffic configuration along Terry Fox Drive – two North-bound lanes open, two South-bound lanes open traffic between approximately Campeau Drive to Hwy 417 WBL exits i.e., no lane closures
  • Encroachment/flagging as necessary, along Didsbury Road East near Earl Grey Drive.

Pedestrian Detours

  • No impacts anticipated, north-bound cyclists and pedestrians along Terry Fox Drive are detoured to the temporary multi-use pathway along the East side of Terry Fox Drive.

OC Transpo Detours

  • No route impacts anticipated.  Temporary Bus Stops applied by OC Transpo along Terry Fox where necessary.

Other

  • Access to residents and business are being maintained
  • Ongoing discussions with the BIA