Earl Grey Drive Extension- 2 Week Look Ahead June 22

June 19, 2026

diagram-arrow-down

Sharing the latest 2-week look ahead update for the Earl Grey Drive project:

Construction

Anticipated construction activities over the next 2 weeks starting June 22nd week

  • Stage 4 traffic remains in place along Terry Fox Drive.
  • Added left turn from Didsbury to Terry Fox.
  • Continue the storm sewer works along Earl Grey Drive and Didsbury Road (east).
  • Continue watermain works along Didsbury Road (east).
  • Continue Terry Fox overpass works, abutments.

Traffic

The following are the current and upcoming traffic impacts for your community.

Lane Closures

Anticipated lane closures over the next 2 weeks, continuing the week of June 22nd:

  • Stage 4 traffic configuration along Terry Fox Drive – two North-bound lanes open, two South-bound lanes open traffic between approximately Campeau Drive to Hwy 417 WBL exits.
  • Encroachment/flagging as necessary, along Didsbury Road East
  • Didsbury Roadway Closure: upcoming July 6th roadway closure for Didsbury Road East at Terry Fox Drive, targeting approximately a 6-week closure period.

Pedestrian Detours

  • No impacts anticipated, north-bound cyclists and pedestrians along Terry Fox Drive are detoured to the temporary multi-use pathway along the East side of Terry Fox Drive.  Commenced on June 1st throughout the Summer the crosswalks will be closed at Didsbury/Roland Michener at the Terry Fox intersection to the westerly side of Terry Fox Drive, easterly N/S crosswalk to remain open.

OC Transpo Detours

  • No route impacts anticipated.  Temporary Bus Stops applied by OC Transpo along Terry Fox where necessary.  Both current bus stops were temporarily relocated slightly northerly commenced on June 1st until end of Summer.

Other

  • Access to residents and business are being maintained.  Note: Access to businesses along Didsbury Road east will be detoured during the July 6th roadway closure for approximately 6 weeks.
  • Ongoing discussions with the BIA
  • Schedule and Traffic impacts are subject to change and are subject to conditions such as weather, material/labour supply and availability, unforeseen items and conditions