Earl Grey Drive Extension – 2 Week Look Ahead November 9

November 14, 2025

diagram-arrow-down

Our team received the following 2 week look ahead update for the Earl Grey Underpass project:

Construction

Anticipated construction activities over the next 2 weeks starting November 9th week

  • Stage 4 traffic in place along Terry Fox
  • Continue installation of shoring system for Terry Fox underpass along westerly side of Terry Fox Drive
  • Deactivation of existing 600mm watermain along a portion of Terry Fox Drive and Didsbury Road (east)
  • Hydro connection works easterly side of Terry Fox Drive (off-road).

Traffic

The following are the current and upcoming traffic impacts for your community.

Lane Closures

Anticipated lane closures over the next 2 weeks, continuing the week of November 9th:

  • Implement Stage 4 traffic configuration – two North-bound lanes open, two South-bound lane open traffic between approximately Campeau Drive to Hwy 417 WBL exits i.e., no lane closures
  • One south-bound lane closure along Terry Fox Drive approaching Campeau planned November 17th depending on weather.
  • Encroachment/flagging along Didsbury Road (east) daytime works.

Pedestrian Detours

  • No impacts anticipated, north-bound cyclists and pedestrians along Terry Fox Drive are detoured to the temporary multi-use pathway along the East side of Terry Fox Drive.

OC Transpo Detours

  • No route impacts anticipated.  Temporary Bus Stops applied by OC Transpo along Terry Fox where necessary.

Other

  • Access to residents and business are being maintained
  • PVMS signs in place
  • Ongoing discussions with the BIA
  • Schedule and Traffic impacts are subject to change and are subject to conditions such as weather, material/labour supply and availability, unforeseen items and conditions