Work Plan:

  • June 1-8 2026 reduction of lanes to facilitate replacement of existing infrastructure that is currently located right in the middle of Terry Fox.
  • JuneĀ  8-15 2026 shift traffic over and complete the works to get outside Terry Fox lanes to open everything back up.

PVMS signs are placed and traffic impacts and PSA will be issued to account for this impact.

There will be more impacts and a road closure along Didsbury, this will be communicated shortly.