Our office just received an update on the status of the Kanata Town Centre Pond Cleanout.
The contractor will be hauling dried sediment from the Village Green Sediment Storage Area, located at 84 Birkendale Drive, to the landfill for the remainder of this week.
Starting next week, the contractor will re-mobilize to the Kanata Town Centre Pond to remove the remainder of the sediment in the pond and begin their site reinstatement work.
Please note that the multi-use pathway around the pond will be closed off to pedestrian access next week from July 7th – July 11th. If all goes according to plan, and weather cooperates, the multi-use pathway should be re-opened to the public the week of July 14th.
We will share further updates as they become available.